溧阳抽水蓄能电站主体工程土石方调配平衡研究
基金项目(Foundation):
邮箱(Email):
DOI: 10.13928/j.cnki.wrahe.2011.07.021
发布时间: 2011-07-20
出版时间: 2011-07-20
移动端阅读
摘要:

针对溧阳抽水蓄能电站工程C1标、C2标的施工方案,较全面系统地分析了土石方施工工程中的影响因素,以及各个方面相互联系和制约关系,进行了土石方调配平衡系统与道路运输系统等的综合优化,以寻求合理的土石方调配方案,达到快速、合理、经济施工之目的。

Abstract:

In allusion to the construction schemes of the bid-sections of C1 and C2 of the construction of Liyang Pumped Storage Hydropower Station,the impact factors from the construction of the earth-rock work are systematically analyzed herein along with the study on the mutually associated and restricted relationships at all the aspects concerned,and then the comprehensive optimizations are made on both the balancing system for the allocation of the earth-rock work and the road transportation system,so as to obtain a reasonable earth-rock work allocation scheme and get the target of quick,reasonable and economic construction.

基本信息:

DOI:10.13928/j.cnki.wrahe.2011.07.021

中图分类号:TV541

引用信息:

[1]肖浩,申明亮,张文熙,等.溧阳抽水蓄能电站主体工程土石方调配平衡研究[J].水利水电技术,2011,42(07):56-59.DOI:10.13928/j.cnki.wrahe.2011.07.021.

发布时间:

2011-07-20

出版时间:

2011-07-20

引用

GB/T 7714-2015 格式引文
MLA格式引文
APA格式引文
检 索 高级检索